Explorer Kit — 30-Day Starter Programme¶
1. Purpose¶
The Explorer Kit provides organisations without AI experience concrete, day-by-day guidance to deliver a working AI prototype within 30 days. All templates are simplified to the minimum necessary.
Who is this for?
This package is designed for Explorer organisations (maturity score 10–20 on the Blueprint Navigator). If your organisation already has multiple AI systems in production, use the Three Tracks or Accelerators instead.
2. What is in the package?¶
| Component | Description | Time investment |
|---|---|---|
| 30-Day Day-by-Day Plan | Weekly planning with daily actions and checkboxes | 30 minutes to read |
| Project Charter Light | 1-page project framework (simplified) | 30–60 minutes to complete |
| Quick Risk Pre-Scan | 15-question risk scan | 20–30 minutes to complete |
| Minimal Validation Report | 2-page validation report | 60–90 minutes to complete |
3. The 30-Day Structure at a Glance¶
Week 1 — Foundation
├── Day 1–2: Fill in Project Charter Light
├── Day 3–4: Complete Quick Risk Pre-Scan
└── Day 5: Assemble team & assign roles
Week 2 — Discovery
├── Day 6–8: Data evaluation (checklist)
└── Day 9–10: Use case selection (scorecard)
Week 3 — Validation
├── Day 11–15: Build prototype
└── Day 16–17: Golden Set test (20 test cases)
Week 4 — Decision
├── Day 18–20: Complete Minimal Validation Report
├── Day 21: Gate 1 Review
└── Day 22–30: Iterate or stop with evidence
4. Prerequisites¶
Before you start, verify the following:
- At least one AI PM or project lead available (50% of their time)
- At least one developer available (80% of their time)
- Access to a dataset or content source for your use case
- Budget for an API key (Claude, OpenAI or equivalent)
- Management commitment for a Go/No-Go decision on day 21
5. How to get started¶
Step 1. Read the 30-Day Plan in full (30 minutes).
Step 2. Complete the Project Charter Light with your team on days 1–2.
Step 3. Conduct the Quick Risk Pre-Scan on days 3–4. A red signal: consult the full Pre-Scan before proceeding.
Step 5. Complete the Minimal Validation Report on days 18–20 as preparation for the Gate 1 Review.
6. Success Metrics¶
| Metric | Target |
|---|---|
| Time to working prototype | \< 25 days |
| Gate 1 Review ready on day 21 | 100% |
| Validation on 20 test cases | ≥ 80% quality score |
| Go/No-Go decision documented | Always |
7. Related Modules¶
- Blueprint Navigator — determine if this package suits you
- Organisation Profile: The Explorer
- Phase 1: Discovery & Strategy
- Phase 2: Validation (Proof of Value)
- Full Project Charter
- Full Risk Pre-Scan