Cheatsheet — Gate Reviews¶
Source: Gate Reviews Checklist
Overview 5 Gates¶
| Gate | After phase | Core question | Minimum deliverables |
|---|---|---|---|
| Gate 1 | Discovery | Is the use case feasible and worth pursuing? | Project Charter, Risk Pre-Scan, Collaboration mode |
| Gate 2 | Validation (PoV) | Has it been proven to work on real data? | Golden Set results, PoV report, Go/No-Go |
| Gate 3 | Development | Is the system production-ready? | AI Safety Checklist, Red Teaming, Model Card |
| Gate 4 | Delivery | Is the handover complete? | Handover checklist, SLA, monitoring plan |
| Gate 5 | Closure | Have the benefits been realised? | Lessons Learned, benefits report |
Decision Options¶
| Decision | Meaning | Required action |
|---|---|---|
| Go | Phase succeeded, start next phase | Document, start next sprint |
| Conditional Go | Proceed with open items | List + owner + deadline established |
| No-Go | Phase failed | Root cause, recovery plan, reschedule gate |
| Stop | Terminate project | Closure report + lessons learned |
Required Attendees¶
| Role | Gate 1 | Gate 2 | Gate 3 | Gate 4 | Gate 5 |
|---|---|---|---|---|---|
| AI PM | ✓ | ✓ | ✓ | ✓ | ✓ |
| Guardian | ✓ | ✓ | ✓ | ✓ | ✓ |
| Tech Lead | ✓ | ✓ | ✓ | ✓ | — |
| Sponsor | ✓ | — | — | ✓ | ✓ |
| CAIO | — | — | High Risk | — | — |
Red Flags per Gate¶
- Gate 1: No measurable success criteria → No-Go
- Gate 2: Golden Set score below threshold → No-Go
- Gate 3: Critical Red Teaming finding still open → block go-live
- Gate 4: Monitoring plan missing → Conditional Go at most
- Gate 5: Benefits not measured → Lessons Learned mandatory
Source for full approach: Gate Reviews Checklist