1. Quick Start: AI Project in 90 Days¶
Purpose
Structured roadmap to go from AI ambition to production-ready deployment in three phases (Focus, Pilot, Scale) within 90 days.
1. Prerequisites (Definition of Ready)¶
- Core team designated: AI Product Manager, Tech Lead, Guardian
- Access to relevant data arranged (minimum read rights)
- Workspace ready: repo/wiki + space for templates + decision log
- One use case selected (max 1) with a clear owner
2. Planning (Week by Week)¶
| Week | Goal | Deliverables (mandatory) | Primary owner | Gate/Output |
|---|---|---|---|---|
| 1 | Use case sharp + scope | Project Charter (concept) | AI PM | Go/no-go on problem definition |
| 2 | Risk + data feasibility | Risk Pre-Scan, Data Evaluation summary | Guardian + Tech Lead | Gate 1 (Go/No-Go Discovery): continue? |
| 3 | Objective + Hard Boundaries | Business Case (v1) | AI PM + Guardian | Hard Boundaries approved |
| 4 | Set up test basis | Golden Set Test + Golden Set v1 | AI PM + QA/Tech | Test plan ready |
| 5 | Prototype (pilot) | Prototype + Gate Review Checklist (concept) | Tech Lead | Internal demo |
| 6 | Measure pilot | Validation Report (pilot) | Tech Lead + AI PM | Gate 2 (Validation Pilot Investment): to Dev? |
| 7 | Development: integration path | Integration plan + logging plan | Tech Lead | Ready for RC |
| 8 | Privacy & security checks | Data & Privacy Sheet | Guardian + Privacy | "OK to proceed" |
| 9 | Build Release Candidate | RC build + Gate Review Checklist (v1); Batch size policy defined and communicated | Tech Lead | RC ready |
| 10 | Test RC & evidence | Validation Report (RC); CI feedback SLOs established (agreed time window) | QA + Guardian | Gate 3 (Production-Ready): Go Live? |
| 11 | Live pilot + monitoring | Monitoring + incident process active; AI-assisted development hard boundaries implemented (mandatory review, test coverage) | Tech Lead | 1st production evaluation |
| 12 | Optimise + handover | Management plan + baseline performance degradation; Regression on Golden Set enforced before RC — Source: [so-28] | Tech Lead + AI PM | Handover Management & Optimisation |
| 13 | Retrospective + standardise | Lessons learned + blueprint updates | AI CC | v2.3 backlog |
3. Minimum Decision Moments (Gates)¶
- Gate 1 (Go/No-Go Discovery) (end of week 2): risk + data feasibility confirmed
- Gate 2 (Validation Pilot Investment) (end of week 6): pilot result (Validation Report) meets Evidence Standards
- Gate 3 (Production-Ready) (end of week 10): RC meets Evidence Standards + logging/privacy arranged
- Gate 4 (Go-Live) (week 12): handover to management incl. baseline performance degradation
4. Timeline per Risk Level¶
The standard 13-week planning is suitable for Limited Risk applications. Adjust the timeline based on your risk classification:
Minimal Risk (Fast Lane): 6-8 weeks¶
| Phase | Weeks | Focus |
|---|---|---|
| Discovery | 1-2 | Charter + Risk Pre-Scan + Objective Card |
| Validation | 3-4 | Prototype + Golden Set (20 cases) + Pilot |
| Go-Live | 5-6 | Validation Report + Monitoring basics |
| Stabilisation | 7-8 | Optimisation + Handover |
See Fast Lane for admission criteria.
Limited Risk: 13 weeks (standard)¶
Follow the week-by-week planning in section 1 above.
High Risk: 18-24 weeks¶
| Phase | Weeks | Additional activities vs standard |
|---|---|---|
| Discovery | 1-3 | Extended DPIA, legal review, Guardian approval |
| Data Governance | 4-6 | Data lineage, extended quality controls, bias analysis |
| Validation | 7-12 | Golden Set (150+ cases), Fairness Check, external audit |
| Development | 13-18 | Extended technical dossier, CE preparation |
| Go-Live & Stabilisation | 19-24 | Phased rollout, intensive monitoring, Guardian reviews |
Additional requirements High Risk:
- Full EU AI Act compliance documentation
- Independent Guardian review at every Gate
- Quantitative Fairness Check with mitigation plan
- 100% input/output logging with 12-month retention
Fast Lane¶
For systems with Minimal Risk, the 13-week roadmap can be shortened to 6–8 weeks:
| Week | Fast Lane activity |
|---|---|
| 1–2 | Project Charter + Risk Pre-Scan (no extended business case) |
| 3–4 | Prototype + quick Validation Pilot (minimal Golden Set: 20 test cases) |
| 5–6 | Validation + direct go-live (Gate 1 + Gate 3 combined) |
| 7–8 | Set up monitoring + first drift measurement |
Fast Lane criteria: Minimal Risk, Mode 1–2, no personal data, internal users only.
Next step: Start with Phase 1: Set Focus & Rationalise → See also: Explorer Kit | Organisation Profiles